Abstract

The increasingly competitive manufacturing industry requires companies to continuously improve productivity, efficiency, and product quality. One of the key factors in achieving production targets is the effective utilization of machines as major assets in the manufacturing process. PT. XYZ is a manufacturing company that uses a Stamping machine as its main production equipment; however, it still experiences several problems such as unexpected breakdowns, long die setup time, reduced production speed, minor stoppages, and defective products, causing production targets to be unmet optimally. This study aims to analyze the effectiveness level of the Stamping machine using the Overall Equipment Effectiveness (OEE) method, identify the components of availability, performance, and quality, and determine the dominant production losses through Six Big Losses analysis. The study was conducted from June to October 2025 using downtime, operating time, production output, and reject product data. The results showed that the average OEE value of the Stamping machine was 74.05%, which is still below the world-class standard of 85%. The availability value was 84.29%, performance was 90.13%, and quality was 97.44%. The largest losses were Breakdown Losses at 28.85%, Setup and Adjustment Losses at 16.43%, and Idling and Minor stoppages at 12.02%. Improvement proposals through preventive maintenance, autonomous maintenance, SMED implementation, 5S program, operator training, and daily inspections are projected to increase the OEE value to 82.15%.

References

Alexander, Y., Putra, F. E., & Sari, P. A. (2024). Implementation of total productive maintenance on frame welding machine maintenance using the overall equipment effectiveness (OEE) method at PT Electronics Components Indonesia. International Journal of Innovative Science and Research Technology (IJISRT), 9, 353–362. https://doi.org/10.38124/ijisrt/IJISRT24JUN909

Aristriyana, E., & Fauzi, R. A. (2023). Analisis penyebab kecacatan produk dengan metode fishbone diagram dan failure mode effect analysis (FMEA) pada Perusahaan Elang Mas Sindang Kasih Ciamis. Jurnal Industrial Galuh, 4(2), 75–85. https://doi.org/10.25157/jig.v4i2.3021

Asmoro, N. D. A., & Widiasih, W. (2022). Analisis keandalan mesin untuk meningkatkan kinerja pada mesin extruder di PT. Rapindo Plastama. Journal of Industrial View, 4(2), 11–22. https://doi.org/10.26905/jiv.v4i2.8014

Bank, J. (1992). The essence of total quality management. Prentice Hall.

Brassard, M., & Ritter, D. (2010). The memory jogger II: A pocket guide of tools for continuous improvement. GOAL/QPC.

Costigliola, F. C. (2019). Library of Congress cataloging in publication data. Awkward Dominion, 381–382. https://doi.org/10.7591/9781501721144-016

Daryus, A. (2019). Manajemen perawatan mesin. Universitas Darma Persada.

De Fretes, R. (2022). Analisis penyebab kerusakan transformator menggunakan metode RCA (fishbone diagram and 5-why analysis) di PT. PLN (Persero) Kantor Pelayanan Kiandarat. Arika, 16(2), 117–124. https://doi.org/10.30598/arika.2022.16.2.117

Doggett, A. M. (2005). Root cause analysis: A framework for tool selection. Quality Management Journal, 12(4), 34–45. https://doi.org/10.1080/10686967.2005.11919269

Eshardiansyah, M. C., Azizah, F. N., & Wahyudin, W. (2024). Analisis mesin CNC milling dengan metode overall equipment effectiveness dalam mendeteksi six big losses di PT. A. Industrika: Jurnal Ilmiah Teknik Industri, 8(2), 227–237. https://doi.org/10.30790/indstrk.v8i2.1249

Gandhi, D. N., & Deshpande, V. (2018). A review of TPM to implement OEE technique in manufacturing industry. Industrial Engineering Journal, 11(6), 36–46. https://doi.org/10.26488/IEJ.11.6.1073

Hadi, S. (2019). Buku perawatan dan perbaikan mesin industri. Andi.

Hansen, R. C. (2001). Overall equipment effectiveness: A powerful production/maintenance tool for increased profits. Industrial Press.

Heizer, J., Render, B., & Munson, C. (2020). Operations management: Sustainability and supply chain management. Pearson.

Hidayat, D. F., Hardono, J., & Santoso, T. M. (2020). Perbaikan waktu set-up menggunakan metode single minute exchange die (SMED) di PT. HP. Journal Industrial Manufacturing, 5(1), 18. https://doi.org/10.31000/jim.v5i1.2431

Irwati, D., & Prasetya, D. I. (2020). Mengurangi cacat color out menggunakan pendekatan seven tools: Studi kasus industri coloring plastic. Jurnal Pelita Industri, 1(1), 16–21.

Kurnia, Y., & Nasarudin, N. (2023). Perbaikan kesehatan dan keselamatan kerja pada proses pembuatan wajan alumunium dengan metode fishbone diagram. Jurnal Industrial Galuh, 5(2), 124–131. https://doi.org/10.25157/jig.v5i2.3311

Lee, C.-Y., Huang, Y.-T., & Chen, P.-J. (2024). Robust-optimization-guiding deep reinforcement learning for chemical material production scheduling. Computers & Chemical Engineering, 187, Article 108745. https://doi.org/10.1016/j.compchemeng.2024.108745

Liker, J. K. (2004). The Toyota way: 14 management principles from the world's greatest manufacturer. McGraw-Hill.

Muchiri, P., & Pintelon, L. (2008). Performance measurement using overall equipment effectiveness (OEE): Literature review and practical application discussion. International Journal of Production Research, 46(13), 3517–3535. https://doi.org/10.1080/00207540601142645

Muhaemin, G., & Nugraha, A. E. (2022). Penerapan total productive maintenance (TPM) pada perawatan mesin cutter di PT. XYZ. Jurnal Ilmiah Wahana Pendidikan, 8(9), 205–219.

Nakajima, S. (1988). Introduction to TPM: Total productive maintenance. Productivity Press.

Ohno, T. (1988). Toyota production system: Beyond large-scale production. Productivity Press.

Onyebuchi, G., & Harcourt, P. (2024). International entrepreneurship and management journal. International Entrepreneurship and Management Journal, 8(2), 113–146.

Owen, S. (2008). Introduction. Richard Hoggart and Cultural Studies, 1–19. https://doi.org/10.1057/9780230583313

Palah, A. M., Setiawan, A. B., & Melani, M. M. (2022). Analisis biaya pemeliharaan alat-alat produksi dengan pendekatan TPM (total productive maintenance): Studi kasus di PT. Kalbe Milko Indonesia [Skripsi tidak diterbitkan].

Pratama, M. A., Kurniawan, F. A., & Irwan, A. (2020). Analisis penerapan total productive maintenance (TPM) melalui metode overall equipment effectiveness (OEE) pada mesin packer di pabrik semen PT. XYZ. JiTEKH, 8(1), 11–21. https://doi.org/10.35447/jitekh.v8i1.305

Robbins, S. P., Coulter, M. K., & Randel, A. (2020). Management. Pearson.

Stevenson, W. J., Hojati, M., Cao, J., Mottaghi, H., & Bakhtiari, B. (2021). Operations management. McGraw-Hill Education.

Sukmoro, W. (2023). OEE demistifikasi. PT Mitra Prima Produktivitas.

Susanto, G. P., & Profita, A. (2023). Analisis kinerja mesin rotary dengan menggunakan metode overall equipment effectiveness (OEE). Jurnal Teknik Industri (JATRI), 1(2), 24–34. https://doi.org/10.30872/jatri.v1i2.1011

Trisliatanto, D. A. (2020). Metodologi penelitian: Panduan penelitian dengan mudah dan lengkap. Andi.

Wibisono, D. (2021). Analisis overall equipment effectiveness (OEE) dalam meminimalisasi six big losses pada mesin bubut (studi kasus di pabrik parts PT XYZ). Jurnal Optimasi Teknik Industri (JOTI), 3(1), 7–13. https://doi.org/10.30998/joti.v3i1.6130

Wireman, T. (2004). Total productive maintenance. Industrial Press.

Wiyatno, T. N., & Kurnia, H. (2022). Increasing overall equipment effectiveness in the computer numerical control lathe machines using the total productive maintenance approach. Jurnal Bayesian: Jurnal Ilmiah Statistika dan Ekonometrika, 2(1), 1–8. https://doi.org/10.31315/opsi.v15i1.7284

Wiyatno, T. N., Putra, F. E., & Khofiyah, N. A. (2025). Line balancing analysis using the rank positional weight method to improve OEE value on the machining line in an Indonesian automotive company. International Journal of Technology and Engineering (IJTE), 1(3). https://doi.org/10.71364/ijte.v1i3.15

Downloads

Published

2026-06-30

How to Cite

Sudarsono Aldi, Tri Ngudi Wiyatno, & Fibi Eko Putra. (2026). Analisis Efektivitas Mesin Stamping melalui Pendekatan Overall Equipment Effectiveness (OEE) dan Six Big Losses di PT. XYZ. Jurnal Multidisiplin Indonesia, 4(2), 642–656. https://doi.org/10.62007/joumi.v4i2.801

Similar Articles

1 2 3 > >> 

You may also start an advanced similarity search for this article.